West Division Street from Brooke Street east to the Fond du Lac River
Schedule: April 20, 2015 to early October 2015
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 31 to September 4: The concrete subcontractor continues paving operations. Concrete flatwork will begin in front of St. Paul’s Cathedral Church.
Traffic Impacts: West Division Street is closed to through traffic. Business traffic should be accessed from Military Road and Brooke Street. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.
Cedar Street from West 12th Street to West 9th Street
Schedule: June 2015 to October 2015
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 31 to September 4: The concrete subcontractor continues the concrete flatwork. The excavation contractor will begin to prep for restoration.
Traffic Impacts: Cedar Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street during working hours.
West 11th Street from South Hickory Street to Ann Street
Schedule: August 2015 to October 2015
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
August 31 to September 4: The concrete contractor will begin flatwork and placement of curb and gutter.
Traffic Impacts: W. 11th Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street during working hours.
9th Street from Linden Street to Center Street
Schedule: July 2015 to October 2015
Description: The project includes reconstruction of the water main, street, and lighting.
August 31 to September 4: The excavation contractor may begin to excavate the roadway.
Traffic Impacts: 9th Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street during working hours.
8th Street from South Main Street to Ellis Street
Schedule: July 2015 to October 2015
Description: The project includes reconstruction of the water main, spot repairs of sidewalk and street.
August 31 to September 4: The utility contractor will be installing the water main.
Traffic Impacts: 8th Street is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street during working hours.