4-23-18 fdl avenue construction update

Fond du Lac Avenue from Sixth Street to North of National Ave
Schedule: April 2018 thru October 2018
Description of work: The project work consists of placing new sanitary sewer, water main, storm sewer, excavation, grading, stone base, asphalt pavement, concrete pavement, curb and gutter, concrete sidewalk, asphalt pedestrian trail, traffic signals, lighting, pavement marking, signing, and landscaping.
April 23rd to April 27th: The contractor will finish installing sanitary laterals, water laterals storm sewer, removing pavement and grading the roadway from 9th Street to 6th Street or Stage 1. The contractor will begin installing water main and side street sanitary main from 9th Street to 11th Street or Stage 2. In addition Alliant Energy will be installing gas main and services from Boyd Street to the south.
Traffic impacts: Fond du Lac Avenue will be closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street during working hours.
Project Detour: South National Avenue at the intersection with Fond du Lac Avenue to Fourth Street at the intersection with Fond du Lac Avenue.
 