10-7-19 fdl weekly construction schedule

East Cotton Street from North Park Avenue to McKinley Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
October 7 th to October 11 th : The grading contractor will complete fine grading and begin paving operations.
Traffic Impacts: East Cotton Street is closed to through traffic. Residents, business owners, and customers may  access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
McKinley Street from Rose Avenue to Stow Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
October 7 th to October 11 th : The grading contractor will complete fine grading and begin paving operations.
Traffic Impacts: Traffic Impacts: McKinley Street is closed to through traffic. Residents, business owners, and  customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Stow Street from McKinley Street to Roosevelt Street
Schedule: May 2019 through September 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
October 7 th to October 11 th : The grading contractor will complete fine grading and begin paving operations.
Traffic Impacts: Stow Street is closed to through traffic. Residents, business owners, and customers may access  properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to  move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Marquette Street from Arndt Street to McWilliams Street
Schedule: July 2019 through October 2019
Description: The project includes reconstruction of the sanitary sewer, water main, storm sewer, street, and lighting.
October 7 th to October 11 th : The utility contractor will finish installing storm sewer main, catch basins and sanitary  sewer main/laterals.
Traffic Impacts: Marquette Street is closed to through traffic. Residents, business owners, and customers may access roperties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Parking is not permitted on the street within the construction zone during working hours.
Arndt Street Bridge Replacement, Arndt Street between Satterlee Street and Lincoln Avenue
Schedule: June 2019 through October 2019
Description: The project includes the replacement of the Arndt Street Bridge over the West Branch of the Fond Du Lac River. This project is a partnership between the City of Fond du Lac and the Wisconsin Department of Transportation (DOT).
October 7 th to October 11 th : The bridge contractor completed forming and pouring the parapets on the new bridge deck. Crews will continue with finish work on the bridge and stripping the false work. The concrete contractor  poured the north approaches and pavement and will start grading the south by weeks’ end.
Traffic Impacts: Arndt Street between Lincoln Ave. and Satterlee Street is closed to thru-traffic. Boat traffic under the structure will be restricted at time as work progresses.
County Road V from Pioneer Road to Fond du Lac Avenue Pioneer Road from Sherwood Boulevard to Wedgewood Road
Schedule: April 2019 through end of November 2019
Description of work: The project includes reconstruction of the water main and services and partnership with Fond  du Lac County for new storm sewer, street, pedestrian trail, and lighting.
October 7 th to October 11 th : Fond du Lac County Highway Dept continues work on storm sewer installation and common excavation on CTH V from Tap Street north.  Electrical Contractor continues to install conduit and bases on
CTH V from CTH VV north to Mequon Avenue.  CTH VV segment, the roundabout and CTH V south of the intersection have first layer of asphalt installed along with all curbs and side walk areas backfilled with top soil.   Concrete contractor scheduled to move back in week of 23th to continue pouring islands, truck aprons and start setting and  installation of the new curb and gutter, sidewalk, and driveways along CTH V north of CTH VV Pioneer Road segment up to Tap Street.
Traffic impacts: County Road V from Fond du Lac Avenue and Pioneer Road is closed to through traffic. Additionally,  Pioneer Road from Sherwood Blvd to Wedgewood Lane is closed to through traffic. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Project Detour: North on Fond du Lac Avenue to South on Martin Avenue to west on Pioneer Road.   Various Bridge Railing Painting: USH 151, Merrill Ave. 9 th St., Grove St. Doty St. and Martin Ave.
Schedule: October 2019 through end of October 2019
Description: The project includes repairs to the deteriorating paint of these bridge railings. Touchup paint work will  take place at each of these bridges.
October 7 th to October 11 th : Crews will be water blasting the railing, removing the loose paint and repair painting  these areas.
Traffic Impacts: At the above-mentioned bridges, there will be equipment along the curb line and some lane  restrictions are possible. Please be cautious when approaching these bridges.